Case study · Industry summit · Hollywood, CA · 2024

A wall 6 m tall, with doors behind it

Published

The SMPTE Media Technology Summit is where the people who set the standards for film and TV meet. In 2024 we put the main LED wall in its ballroom, sponsored in the name of Gloshine, the panel maker. The room gave us a narrow space, a lot of height, and doors right behind the wall.

October 24, 2024: the same wall at the SMPTE Awards Gala
October 24, 2024: the same wall at the SMPTE Awards Gala
  • The finished wall on test content
  • Test content, the crew still on the lift
  • Playback and processing

At a glance

Event
SMPTE Media Technology Summit 2024 and SMPTE Awards Gala
Venue
Ray Dolby Ballroom, Ovation Hollywood, Los Angeles
Dates
October 21–24, 2024, gala on October 24 (load-in from October 19)
Our role
LED wall and processing, sponsored in Gloshine’s name; our own crew and equipment
LED
Gloshine MV Pro 2.6, 7680 Hz refresh
Size
5 m wide × 6 m high (16.4 × 19.7 ft), 120 cabinets, portrait
Resolution
1920 × 2304
Processing
NovaStar MX40 Pro
Structure
Free-standing: four truss towers, ballasted base, rear braces
Crew
Six

The brief

SMPTE, the Society of Motion Picture and Television Engineers, holds its Media Technology Summit in Hollywood every year, and closes it with the Awards Gala. In 2024 we arranged to sponsor the summit’s main LED wall under the name of Gloshine, whose panels we use, and supplied it with our own crew and equipment.

Our part was the LED wall and its processing. Lighting and sound in the room were not ours.

Have a project in mind? Send us the details, or call.

Challenge 01

Narrow, very tall, and doors behind it

The space for the wall was not wide, but it was tall, so the wall went up rather than across: 5 m wide and 6 m high, 10 cabinets across and 12 high.

Right behind it were doors. Nothing could be fixed to the wall, so the screen had to stand on its own. We built a structure of four truss towers on a base of truss and deck, weighed it down with ballast, and braced it from behind. The cabinets hang between the towers.

Six meters of LED, held up by nothing but its own frame.

October 19: the truss towers going up, the room’s doors behind them
October 19: the truss towers going up, the room’s doors behind them
Behind the finished wall: towers, ballast and braces. Peter Lin on site
Behind the finished wall: towers, ballast and braces. Peter Lin on site

For the SMPTE Media Technology Summit 2024 (October 21–24) and the SMPTE Awards Gala on its last evening, in the Ray Dolby Ballroom at Ovation Hollywood, PixelPro Productions supplied, built and ran the main LED wall, sponsored in the name of Gloshine. The wall is 5 m wide and 6 m high (about 16.4 × 19.7 ft): 120 Gloshine MV Pro 2.6 cabinets, 1920 × 2304 pixels at 7680 Hz, on NovaStar MX40 Pro processing. There were doors behind it, so it could not be fixed to the wall: it stands on its own structure of four truss towers on a ballasted base, braced from behind, built from a scissor lift by a crew of six. The same wall carried the summit sessions by day and the gala that closed the event.

Challenge 02

Twelve rows, from a scissor lift

At six meters, every row above the first few was hung from a scissor lift. We brought the wall up a row at a time, with every cabinet showing its port and position on a test card so that each one was in the right place before the next row went on.

Once all 120 cabinets were in, the whole wall went to white to check the color, then to test content.

Each cabinet labeled with its port and number on the test card
Each cabinet labeled with its port and number on the test card
All 120 cabinets on white, checking the color
All 120 cabinets on white, checking the color

Challenge 03

One wall, a summit by day and a gala by night

The summit sessions and the gala were in the same room. By day the wall carried the summit’s sessions; on the last evening it carried the Awards Gala, with the room reset around it.

We ran the processing for the whole event.

A summit session: the wall’s full height in use
A summit session: the wall’s full height in use
The gala on October 24, the same wall
The gala on October 24, the same wall

The result

  • A 5 × 6 m LED wall, standing on its own frame, in front of the room’s doors.
  • 120 Gloshine MV Pro 2.6 cabinets, 1920 × 2304, on NovaStar MX40 Pro.
  • One wall for the whole event: summit sessions and the Awards Gala.
  • Built and run by our own crew of six, on our own equipment.

How we run LED and crew for events is on our event AV production page.

The same panels are in our rental stock: see LED screen rental.

Questions event planners ask

Can an LED wall stand on its own without being fixed to the room?

Yes. At the SMPTE Media Technology Summit 2024 in Hollywood there were doors behind the wall, so nothing could be fixed to the room. PixelPro built a 5 × 6 m LED wall on four truss towers on a ballasted base, braced from behind, and hung the cabinets between the towers.

How tall can a ground-stacked LED wall be?

It depends on the structure under it. At the SMPTE Media Technology Summit 2024 PixelPro built a portrait LED wall 6 m high and 5 m wide, 120 Gloshine MV Pro 2.6 cabinets, on its own truss towers with ballast and rear braces, working from a scissor lift.

Can one LED wall serve both conference sessions and an awards gala?

Yes, in the same room. At the SMPTE Media Technology Summit 2024 the same 5 × 6 m wall in the Ray Dolby Ballroom carried the summit sessions by day and the SMPTE Awards Gala on the last evening, on NovaStar MX40 Pro processing.