LED rental · Moscone Center, San Francisco

LED wallsat Moscone Center, San Francisco

LED walls for booths and sessions at Moscone Center, shipped from our warehouse in Anaheim. Moscone runs on union labor, so this page explains who builds the wall, what to plan, and when, from the venue’s own rules.

Our warehouse in Anaheim, where the walls ship from
Our warehouse in Anaheim, where the walls ship from
  • Cabinets, cased to ship
  • Bay Area: a launch in East Palo Alto
  • A flown wall at Comic-Con

How a wall goes up at Moscone

LED cabinets, cased and ready to ship
LED cabinets, cased and ready to ship

At Moscone the hands-on work is union work. The venue lists “electronic digital signs, video walls, monitors” under Sign and Display Workers Local 510 for exhibits, and the 2026 guide of Projection, its in-house AV company, requires IATSE Local 16 for audiovisual set-up. Which applies to your wall is settled with the show’s contractor.

What we do. Before the show, we size the wall, its processing and its power from your booth drawings, and send the weights and the build steps to the show’s contractor. We ship the wall, the processors, spares and cables from Anaheim to the show’s advance warehouse, or straight to the docks at the show’s move-in time. On site, the union crew builds the wall; we plan the labor with the show’s contractor, and quote a technician of ours if you want one there.

Who builds
Union crews: Local 510 for exhibit displays, IATSE Local 16 for AV, as the show’s contractor sets
Exhibitor self-setup
One person, under half an hour, no tools (ABAI 2026 rule)
Power
The show’s electrical contractor, for anything 20 A or more
Freight
The show’s general contractor; Moscone has no shipping, receiving or storage
Internet
Moscone Facility Services, exclusive
LED cabinets, cased and ready to ship
LED cabinets, cased and ready to ship
NovaStar processing in stock
NovaStar processing in stock

PixelPro Productions rents LED walls for booths and sessions at Moscone Center in San Francisco, shipped from its warehouse in Anaheim, California. Moscone runs on union labor: the venue lists video walls under Sign and Display Workers Local 510 for exhibits, Projection’s 2026 guide requires IATSE Local 16 for audiovisual set-up, and at current shows an exhibitor may set up only what one person can do in half an hour without tools. Projection is the preferred, not exclusive, AV company, but it alone runs the house sound, and the venue’s House Head, a union steward, must be used on large productions whoever supplies the AV. Power of 20 A or more comes from the show’s electrical contractor; internet is Moscone Facility Services’ alone; freight goes through the show’s general contractor. Rigged items of 1,000 lb or more need plans 30 days before move-in, and a freestanding structure 12 ft or taller without an engineer’s stamp must be tied off. Walls are quoted to the show: the wall, processing and freight from Anaheim, with union labor through the show’s contractor.

Walls and prices

At Moscone we quote to the show: the wall, its processing, spares and freight from Anaheim, and a technician of ours if you want one. Union labor is ordered through the show’s contractor and billed by them. Send the booth drawings and the show’s labor rules, and we reply with a price.

Our wall sizes →

The Moscone rules, in seven numbers

From the venue’s own pages, and what each one means for an LED wall.

  • 510 / 16

    Union crews build the wall

    Local 510 for exhibit displays, video walls included; IATSE Local 16 for AV set-up. The show’s contractor sets which.

  • ½ hour

    What an exhibitor may set up alone

    One person, without tools, in under half an hour (ABAI 2026). Anything more is union labor.

  • 20 A

    Power from the show’s electrician

    Anything 20 A or more is installed by the electrical contractor the show names, not by Moscone.

  • 12 ft

    Tie off a tall freestanding wall

    A freestanding structure 12 ft or taller without an engineer’s stamp is tied off to rig points.

  • 16 ft

    Taller booths need approval

    Over 16 ft, the Fire Marshal approves; shows have asked for plans stamped by a structural engineer.

  • 30 days

    Rigging plans

    For anything hung that weighs 1,000 lb or more, before move-in. The House Head has authority over all rigging.

  • 60 days

    Exhibit floor plans

    The show sends them to the Fire Marshal; plans for AV and keynote rooms are due 45 days before move-in.

Which space fits the wall

SpaceCeilingFloor loadCeiling rigging limit
South, Halls A–C37 ft125 lb/sq ft2,000 lb per eyebolt
North, Hall F28 ft125 lb/sq ft2,000 lb per eyebolt
North, Hall E24 ft125 lb/sq ft1,000 lb per eyebolt
West, Level 1 hall27 ft125 lb/sq ft5,000 lb
West, Levels 2 and 326 ft125 lb/sq ft5,000 lb, from the white steel beams
South, Esplanade Ballroom28 ftnot listed500 lb; 2,500 lb on six rows at the south end
South, San Francisco Ballroom (Level 2)25 ft100 lb/sq ft2,500 lb
South, Level 3 rooms15 ft100 lb/sq ft2,500 lb

Hall C has lower-ceiling areas that the floor plan does not give. Largest freight elevator: West Elevator 4, 10 × 11 × 29 ft, 30,000 lb. Two-story and covered booths need at least 24 ft of ceiling and are not allowed in the West lobbies.

Source: Moscone Center: Union Jurisdictions, Rigging Rules, Electrical Contractor Guidelines, Freight Handling, Floor & Elevator Load Ratings, Fire Marshal Floor Plan Requirements, floor plans (moscone.com, 2026); Projection, IATSE Local 16 Event Regulations Guide 2026; ABAI 2026 exhibitor kit (self-setup rule). Show rules differ: check your exhibitor manual.

Questions about LED walls at Moscone Center

Can my own crew set up an LED wall at Moscone?

Usually not. Moscone lists video walls under Sign and Display Workers Local 510 for exhibit set-up, and IATSE Local 16 handles audiovisual set-up. At current shows an exhibitor may set up alone only what one person can do in under half an hour without tools. The show’s contractor tells you which crew builds your wall.

Can I bring my own AV company to Moscone Center?

Yes. Projection is the venue’s preferred AV company, not an exclusive one. But Projection alone runs the house sound, so an outside company brings its own standalone sound. On general sessions and large productions with large-scale video, the venue’s House Head, a billable union steward, must be used whoever supplies the AV.

Who supplies power for an LED wall at Moscone?

The licensed electrical contractor the show names, not Moscone. Anything that needs 20 A or more is installed by that contractor, and at shows we have checked, power of 100 A or more comes down from the overhead catwalks.

Does a tall LED wall need an engineer’s stamp at Moscone?

A freestanding structure 12 ft or taller without an engineer’s stamp must be tied off to rig points. Booths over 16 ft need the Fire Marshal’s approval, and shows have asked for plans stamped by a licensed structural engineer.

How do you get an LED wall to Moscone from Southern California?

We ship the wall, its processors and spares from our Anaheim warehouse, either to the show’s advance warehouse or to the docks at the show’s move-in time. Moscone itself has no shipping, receiving or storage: the show’s general contractor handles all freight, and exhibitors may not drive forklifts.

How much is an LED wall at Moscone Center?

It is quoted to the show: the wall, processing, spares and freight from Anaheim, plus a technician of ours if you want one. Union labor is ordered through the show’s contractor and billed by them. Send the booth drawings and we reply with a price.

CallTextWhatsAppGet a quote